This project consists of the installation of approximately 172 linear feet steel sheet pile with reinforced concrete cap and additional revetment. The seawall will cross the eastern end of Porpoise Point Drive and tie into an existing seawall to the south and existing rock revetment to the north.

Anticipated Schedule

St Johns County’s contractor, Construct Co, Inc, has completed sheet piling and has reached final depth. Welding and cap work has been completed. The project is still on schedule to be completed by early 2024.