Ponte Vedra – South Ponte Vedra Coastal Storm Risk Management

Announcements

Preliminary Beach Trolley Concept Meeting

On October 7, 2026, St. Johns County hosted a community meeting to introduce a preliminary concept for a beach trolley system that could serve South Ponte Vedra Beach and Vilano Beach. – click here for additional information and meeting materials!

Project Overview

  • This project is a 50-year federal partnership with the U.S. Army Corps of Engineers (USACE).  
  • Project extends from 2589 SPV Blvd to just south of the SPV Ocean Club (formerly Serenata Beach Club), from FDEP reference monuments R-78 to R-103.5. 
  • Initial construction is potentially slated for 2029, with 10-year renourishment intervals.  
  • Initial construction of this project would place 2.15 million cubic yards of sand along the project shoreline. 
  • Pre-construction Engineering and Design for this project is slated to begin November 2026. 
  • The project will require 251 easements for privately-owned parcels within the project limits.  
  • Shoreline is eligible for FCCE renourishments after large storm events at no cost to the County.  

Funding

  • County staff are currently exploring potential funding sources for the construction of this project. Public access plays a major role in decreasing the local share. 
  • The proposed Beach Trolley project would enhance public access in this section of St. Johns County’s coastline and increase federal cost-sharing responsibilities while lowering local cost-share responsibilities.  
  • With current conditions, the local cost share for the total 50-year project is estimated to be 69%, or $94,800,000 without a trolley system. 
  • If a trolley system were added to the South Ponte Vedra area, the local cost share for the total 50-year project would be reduced to 47%, or $65,500,000.   
  • With a trolley system, the initial local construction cost would be reduced by $14.4 million dollars. 

Anticipated Timeline

Project is currently projected for kickoff in November 2026. Initial construction is projected to take place in the Summer of 2029.