Ponte Vedra Beach Restoration Project
Announcements
St. Johns County Hosts Ceremony for $38 Million Ponte Vedra Beach Restoration Project – YouTube
Mickler’s Landing Status: Mickler’s Landing is currently OPEN to the public.
- Intermittent closures of Mickler’s Landing are expected as the project progresses. There will be no closures during observed County holidays. Please check back here for updates.
- Construction is underway as of March 29, 2024.
- Crews have begun planting dune vegetation in completed fill areas and installing post & rope at public access points as of April 15, 2024.
- Please click the buttons below for additional project details. PLEASE NOTE: The anticipated schedule is subject to change. The schedule will be updated on at least a weekly basis (last revised: April 22, 2024).
Previous Meetings
- Board of County Commissioners: At the February 20th, 2024 Board of County Commissioners meeting, the contractor Weeks Marine was selected. A recording of the meeting may be viewed here: Meeting Presentation
- St. Johns County Set to Begin $38.6 Million Ponte Vedra Beach Restoration Project: Ponte Vedra Beach Restoration Project Begins – St. Johns County (sjcfl.us)
- Erosion Control Line (ECL) Workshop was held on Thursday, October 26, 6-8 pm at GTMNERR, 505 Guana River Rd. The purpose of this meeting was for the Florida Department of Environmental Protection to consider the location of a proposed Erosion Control Line (ECL) in Ponte Vedra Beach, FL. Proposed Erosion Control Line Map | Meeting Presentation
- The ECL was recorded at the end of December 2023.
- Open House public meetings were held on October 2, and October 10, 6-8pm at the Ponte Vedra Concert Hall to discuss this project. Beach Nourishment Community Meeting 10/2/2023 – YouTube | Meeting Presentation
Overview
- Project Description
- St. Johns County has secured permits to place approximately two million cubic yards of sand on the beaches in Ponte Vedra Beach between the Duval County line to the north, and the Guana Tolomato Matanzas National Estuarine Research Reserve to the south.
- The sand will be brought in to construct a dune and berm system throughout the project area.
- The project will dredge sand from the permitted offshore borrow site out in federal waters and pump it onto the beach with large pipes, where it will be shaped by into position by heavy equipment.
- This project will enhance the dune system by adding sand at the seaward edge of the existing dune, planting sea oats and supporting vegetation, and creating a more uniform front to the dune system within the project area.
- Project Location
- 8.9 miles of Ponte Vedra Beach, from the County line to GTM.
- Environmental Considerations
- Per the permit the dredging ship will be required to have Right Whale monitors on board. The ships speed will also be restricted during Right Whale season.
Funding
The County has secured over $30 million form the State towards the construction of the project, which is estimated to cost approximately $40 million. Likewise, the County has committed over $8 million to the project cost.
Once constructed, and a maintenance/monitoring plan is in place, the project could be eligible for post-disaster funding assistance from FEMA and the FL DEM in the event the project is damaged in a declared disaster.
Anticipated Timeline
Please note that dates are subject to change due to unanticipated delays such as weather.
- Mobilization
- Started: March 18
- Completed: early-April
- Construction
- Started: March 29
- Anticipated completion: mid-August
- Demobilization
- Anticipated start: mid-late August
- Anticipated completion: late-August
FAQ
Frequently Asked Questions:
- Will Mickler’s be impacted for the whole duration of the project?
- Mickler’s will be temporarily closed for mobilization (end of March) and demobilization (expected mid-August).
- There is a possibility for intermittent closures throughout the project.
- Any closures to Mickler’s will be advertised to the public and posted on this website under “Announcements”.
- What are the anticipated hours?
- Dredging and sand placement will occur 24 hours a day, 7 days a week.
- Will it be loud near the active construction site?
- Please expect there to be beeping noises and the movement of heavy machinery (bulldozers) within active construction areas.
- How will the new dunes be preserved?
- Planting crews will be following shortly after construction to plant dune vegetation.
- Post and rope will be installed at public access points to assist in guiding pedestrian activity.
- “Stay Off the Dune” signs are available to beachfront residents, to install at the toe of the new dune. Please email or call us for more information.
The Beach Brief – An E-newsletter for Timely Updates on St. Johns County Beach Projects
St. Johns County remains dedicated to providing our residents, visitors, and businesses with timely and accurate information regarding current and upcoming St. Johns County beach projects. The monthly “Beach Brief” provides subscribers with an overview of beach renourishment, dune enhancement, and other major coastal projects.